Pompano Beach shuts marine passage during critical bridge demolition
Pompano Beach, Florida – For 10 days, one of Pompano Beach’s key marine passages will go quiet beneath McNab Road. Beginning Wednesday, July 22, no boats will be allowed to travel under the bridge as crews move into one of the most sensitive stages of a major reconstruction project.
The short-term shutdown is designed to prevent a far bigger risk. Heavy machinery, bridge demolition, debris removal and structural work will be taking place directly above the navigational channel, leaving no safe way for marine traffic to pass through while the work is underway.
City officials are urging boaters, marina operators and others who use the waterway to adjust their plans before the closure begins. The restriction will apply to all navigation beneath the McNab Road Bridge and is expected to remain in place for 10 days. Should the schedule change, the city said it will issue an update.
“Safety remains our highest priority throughout this project,” Mayor Rex Hardin said.
“While we recognize this temporary closure will impact boaters, it is a necessary step to safely complete this important infrastructure investment. We appreciate the patience and cooperation of our residents and the marine community as we work to deliver a modern bridge that will serve Pompano Beach for generations.”
The work is part of the McNab Road Streetscape and Bridge Replacement Project, an investment connected to the voter-approved 2018 “G.O. Pompano!” Bond Program. While the immediate focus is on demolition and reconstruction, the finished bridge is expected to bring a wider set of improvements for people traveling both on the road and on the water.
Plans call for a safer and more resilient structure, upgraded infrastructure and improved facilities for pedestrians and bicyclists. The replacement is also expected to provide greater vertical and horizontal clearance for marine navigation, a significant long-term benefit for boaters who regularly pass through the area.
The closure comes during a critical construction window, when crews need full control of the space below the bridge. By removing vessel traffic from the channel, workers can operate heavy equipment and complete overhead structural tasks without putting boaters or construction personnel in danger.
The city acknowledged that the temporary interruption will affect residents, businesses, commuters and the broader marine community. Officials are asking for continued patience as the project advances toward completion.
Once finished, the new McNab Road Bridge is intended to create a stronger connection across Pompano Beach while improving movement by land, bicycle, foot and water.
Project updates and additional information are available at www.pompanobeachfl.gov and through the City of Pompano Beach’s social media channels.